Overview
January 2017
Agreement between CVG and Amazon
May 2017
Working in partnership with DHL’s existing operations and facilities
- Amazon operating 18 aircraft based out of CVG for total of 36 daily flights
- Project team initiated permitting and regulatory processes
Spring 2019
Site preparation activity and groundbreaking of South development Phase 1
South development, approximately 650 acres
North development option, approximately 475 acres as lease option
Support of the Amazon Project and CVG from many sides:
2021
Anticipated Phase I project completion/South development
In Process
- Clearing and preparation of land for Phase 1/South development
- Ongoing infrastructure support from CVG and other entities, leading up to 2021 facility opening and beyond, including but not limited to utility and roadway improvements.
Regional Community Impact
- 2000+ job creation
- $1.5 billion project investment